Priority 30 Years of Experience

CLEMENGER

Clemenger is one of Australia’s most creative advertising agencies working with many high profile businesses and brands, with offices throughout Australia.

After a review of accommodation options Clemenger decided to take a full floor in 545 Queen Street - a recently refurbished building with a 4 star Green Star rating and 4.5 star NABERS Energy rating. With the decision made to relocate mid-November 2009, they needed staff relocated and operational before Christmas. To make this happen Priority had to respond quickly and develop a plan for them to achieve this and we advised that the work needed to be scheduled in 3 stages:

Stage 1 – Set up the open plan area with 54 workstations with screens, data and power points. Having workstations set up first would allow them to relocate while other works continued. This was a challenge as workstations and screens have long lead-times.

Stage 2 – Install essential services, air-conditioning, additional electrical as well as install office joinery and painting over the Christmas period while most staff are on leave.

Stage 3 – Construct the front of house facilities - Reception, Meeting Rooms, Boardroom and Breakout area. This stage had to be well planned and coordinated, as their staff would be working next to a construction site.

This was a well-planned and fast-paced project for everyone involved. Priority’s experience and ability to manage construction and control suppliers while the space was occupied made it possible for this work to be done in such an extremely short timeframe. The final result is a well-designed fitout that communicates their level of professionalism, innovation and creativity, entwining a highly positive experience for staff and clients.

  • clemenger
  • clemenger
  • clemenger
  • clemenger
  • clemenger
  • clemenger
  • clemenger
  • clemenger
Project Details

Clemenger Office Fitout
Level 7, 545 Queen Street
Total Floor Area: 750m2

Project Schedule:
Pre-construction: 3 Weeks
Construction: 10 weeks

Project Team
Design: Whitehead Design
Project Manager: Peter Lewis
Project Administrator: Dean Robertson
Project Estimator: David Goldsmith

“To get the outcome you want, you need to be able to rely on the partnership. We chose to go with Priority because of the great relationship we have with Peter Lewis.”

Michael Neilsen, Financial Director – Clemenger

Project Scope

  • Open-plan reception, waiting area and café style staffroom with breakout
  • 10 x seat boardroom
  • 2 x front of house meeting rooms
  • Open-plan work area
  • 2 x internal meeting rooms
  • Kitchenette
  • Finishes
  • Corian stone bench tops
  • Veneer joinery & custom joinery
  • Glass splashbacks
  • Feature circular bulkhead
  • Glazed feature tiles
  • Branded glazed film
  • Custom furniture

Sustainability Checklist

  • 4 Star Green Star Rating
  • 4.5 Star NABERS Energy Rating
  • Indoor Environment Quality
  • Low VOC paint
  • Extensive natural light with external views
  • Materials
  • Boral Enviroboard – low voc & 10% recycled material
  • Energy
  • Re-used base building low energy lighting with zoning and sensor controls
  • Re-used existing ac system and zoning system
  • Energy efficient white goods
  • Solar blocking blinds to reduce heat and glare
  • Transport
  • Easy access to existing public transport
 
Push to Call Us Now